| I. Introduction- We had better weather in May which in turn helped bring production back to a more normal level. |
| II. April Progress |
| |
A. Concrete |
| |
|
* Concrete footings for the front canopy, north dance studio wall, and the front entry were completed. |
| |
|
* Column pad footings for the back second level storage area were completed. |
| |
|
* Column pad footings for the second level Boom Box areas at the sides of theater were completed. |
| |
B. Masonry |
| |
|
* The masonry block at the Stage and Wings area was topped out at the 52’ height. |
| |
|
* The masonry block on the north wall of the dance studio was completed. |
| |
|
* The masonry block on the interior corridor wall from the theater to the north end was completed (front entry). |
| |
|
* The masonry block at the west wall of the locker room/restroom area was completed. |
| |
|
* The masonry block from joist bearing height to the top of the wall was completed on the west wall of the Dance Studio. |
| |
|
* The masonry block from joist bearing height to the top of the wall was completed on the south wall of the Scene Storage area. |
| |
|
* Currently, the mason is working on grouting in pockets where beam and joist ends bear (after welds are approved). About 1/3 completed. |
| |
C. Structural Steel. |
| |
|
* Second level Storage mezzanine steel was completed at the south end of the building. |
| |
|
* Bar joists were set over the Scene Storage area. |
| |
|
* Bar joists were set over the Rehearsal Studio. |
| |
|
* Bar joists were set over the Dance Studio. |
| |
|
* Beams were set over the Stage and Wings area. |
| |
|
* Steel columns, beams, and cross bracing were set at the back of the theater area. |
| |
|
* Steel joists are all nearly set over the theater area. |
| |
|
* With the exception of the Theater area, most of the joists and beams have been welded into place. |
| |
D. Smoke Vents |
| |
|
* The 3 large 6’x6’ smoke vents above the Stage and Wings area have been installed. |
| |
E. Electrical |
| |
|
* Electrician continues with rough-ins. Starting to work on underfloor
rough-ins. |
| III. Scheduled work next 4 weeks. |
| |
A. Masonry |
| |
|
* Will finish the grouting of beam and joist pockets. Will finish north wall of the lobby area following the removal of the crane. |
| |
|
* Will begin laying burnished block and brick in the next 2-3 weeks weather permitting. |
| |
B. Structural Steel |
| |
|
* Erector hopes to be done with the crane this week. |
| |
|
* Will begin roof decking this week and will continue until completed. |
| |
|
* Will be working on catwalks in theater area. |
| |
|
* Will be working on all other miscellaneous detailing/welding work for the majority of the next month. |
| |
C. Electrical - The electrician will continue with rough-ins. |
| |
D. Mechanical - The mechanical subcontractor will be working on rough-ins within the restroom areas. |
| |
E. Concrete - Concrete floors will start in approximately 2-3 weeks weather permitting. |
| |
F. Roofing - Roofing scheduled to start in approximately 3 weeks weather permitting. |
| |
G. Concrete Paving - Concrete paving at west entry to be poured within the next two weeks. |